Hi folks,
This is today. I will be shutting the cluster down shortly. I will
be in NH tomorrow afternoon and evening, so I probably won't be able to
get the cluster back up again until the 31st.
-Josiah
On 12/18/14, 11:22 AM, Thomas Helmuth wrote:
> Thanks for the heads-up Josiah!
>
> On Thu, Dec 18, 2014 at 11:07 AM, Wm. Josiah Erikson
> <wjerikson at hampshire.edu <mailto:wjerikson at hampshire.edu>> wrote:
>
> Hi guys,
> Because of the below, I will need to shut down the cluster
> entirely on December 29th, and unplug it to prevent it coming back
> on automatically when power comes back (because it'll go out again
> shortly afterwards). If I'm around, I'll plug it back in on
> December 30th after they're done, or December 31, and email the
> list after that happens.
> All the best and sorry for the inconvenience.
> -Josiah
>
>
>
> -------- Forwarded Message --------
> Subject: Power Shutdown and Testing
> Date: Thu, 18 Dec 2014 09:33:59 -0500
> From: Larry Archey <larchey at hampshire.edu>
> <mailto:larchey at hampshire.edu>
> To: Joanna Olin <jlcpr at hampshire.edu>
> <mailto:jlcpr at hampshire.edu>, Raymond E. LaBarre
> <rlabarre at mtholyoke.edu> <mailto:rlabarre at mtholyoke.edu>,
> Lachance, James <James.Lachance at cafebonappetit.com>
> <mailto:James.Lachance at cafebonappetit.com>, Chelvanaya B. Gabriel
> <cbgNS at HAMPSHIRE.EDU> <mailto:cbgNS at HAMPSHIRE.EDU>, Jason M. Tor
> <jtor at hampshire.edu> <mailto:jtor at hampshire.edu>, Bob Crowley
> <rlcLO at hampshire.edu> <mailto:rlcLO at hampshire.edu>, Wm. Josiah
> Erikson <wjerikson at hampshire.edu>
> <mailto:wjerikson at hampshire.edu>, Sandy Chessey
> <schessey at hampshire.edu> <mailto:schessey at hampshire.edu>, Jennifer
> Gunter King <jking at hampshire.edu> <mailto:jking at hampshire.edu>,
> Byron P. McCrae <bmccrae at hampshire.edu>
> <mailto:bmccrae at hampshire.edu>, Pam Tinto <ptinto at hampshire.edu>
> <mailto:ptinto at hampshire.edu>
> CC: Carl Weber <CWeber at hampshire.edu>
> <mailto:CWeber at hampshire.edu>, Jeff Neumann <jjnPP at hampshire.edu>
> <mailto:jjnPP at hampshire.edu>
>
>
>
> Good Morning,
>
> I am writing in advance of posting a campus announcement that power will
> be turned off for 3 - 4 hours at FPH, Prescott, Arts Village and Cole
> Science on Tuesday morning, December 30 while repairs are being made to
> the main electrical switchgear. Generator power will be provided to Cole
> Science to maintain critical functions. Power to all other locations on
> campus will remain on during that period. The work being done is to
> install devices designed to prevent the power outage encountered at
> Thanksgiving and to protect critical equipment from being damage from
> electrical power surges.
>
> Once the work is completed, the emergency generators will be tested.
> This will cause 5 - 7 minute mini outages throughout the campus.
> Facilities & Grounds will have electricians on campus to support the
> utility firms doing the work.
>
> Thanks,
>
> Larry
>
> --
> Lawrence M. Archey
> Director of Facilities & Grounds
> Hampshire College
> Amherst, Ma
> (413) 559-5431
>
>
>
>
> _______________________________________________
> Clusterusers mailing list
> Clusterusers at lists.hampshire.edu
> <mailto:Clusterusers at lists.hampshire.edu>
> https://lists.hampshire.edu/mailman/listinfo/clusterusers
>
--
-----
Wm. Josiah Erikson
Head, Systems and Networking
Hampshire College
Amherst, MA 01002
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://lists.hampshire.edu/pipermail/clusterusers/attachments/20141229/2ae05a62/attachment.html>
More information about the Clusterusers
mailing list